SCOPE OF WORK

A&P Engineers served as the Designer of Record for this reconstruction project. In this project, our responsibilities included preparing a Contract Plans Set for the total reconstruction of a 2.0 mile segment of this urban corridor. During this reconstruction, 1 signalized intersection was upgrade from span-wire to mast-arm, multiple traffic safety study recommendation were implemented, ADA facilities were upgraded, a new drainage system was installed, signing and pavement markings were installed, and a new street lighting system was installed.

CLIENT

Miami-Dade County Public Works Department.

LOCATION

S.W. 62nd Avenue from S.W. 24th Street to N.W. 7th Street, Miami, Florida